The reconstruction of another small hydropower plant has been completed near Favorit château, within the municipality of Šindelová in the Karlovy Vary Region.
Our company is already familiar with this small hydropower plant, which has two Bánki turbines on the Skřiváň stream near the rococo Favorit hunting château.
The plant, with a total output of 120 kW, had already undergone reconstruction in the early 1990s. The current customer needed to meet the requirements of the Czech Energy Regulatory Office (ERÚ) for a higher purchase tariff, so a further partial reconstruction of the electrical equipment was undertaken. Elektro Kotouč s.r.o. of Sokolov designed the project and served as the general contractor. Our company supplied the control system and debugged the associated software.
The control system is based on the UNITRONICS Vision 570 PLC with a 5.7-inch colour touchscreen. The processing unit has enough capacity to control and optimise both turbines and to record all operating values on an external SD card at ten-minute intervals. The project also allows for a future addition of a trash rack cleaning machine.
External communication is provided, as usual, by a CINTERION MC35i GSM modem. Owing to the weak signal at the site, it is supplemented by a directional Yagi 12 dB antenna.